Your Company

Kosel Treehouse,

Individual Self-Build in Helston South & Meneage

Completed: 2025


About this home:

This bespoke treehouse was built by Many Hands with utmost attention to detail. They received the plans from retired architect Clive Feather and had to engineer the ambitious design. Designed to have a green roof with a wet weight of 13.5 tonnes, it was a feat of engineering to suspend the building in the trees on screw pile stilts. The main structure was prefabricated and CNC cut off-site for precision and speed. Vertical panelling wraps the curved façade, mirroring the trees that will eventually surround the home. Custom made furniture and complicated details showcase skilled carpentry and make a elaborate shape look effortless. With a luxurious wood burner and outdoor bath, it's an idyllic 2-bedroom retreat in the canopy.


Features:

Individual Self-Build icon

Individual Self-Build

Offsite Construction icon

Offsite Construction

Timber Frame icon

Timber Frame

Solar Panels icon

Solar Panels

Officer Delegated Decision icon

Officer Delegated Decision

Building close to trees icon

Building close to trees

Challenging Access icon

Challenging Access

Accessible Design icon

Accessible Design

Landscape House icon

Landscape House


Planning Insights:

12 months at planning

Having already got permission for the first two treehouses on site, the principle of development and intent was established. Developing on a heritage site in open countryside required sympathetic consideration of visual impact and environment. They have planted 4000 trees across the site to restore the livestock field to woodland, which helps to justify the disruption of building. The economic benefit of the business to the local economy and commitment to being low-impact swayed the decision.



Project Challenges

Sensitive environment of heritage site

The Iron Age fort at the top of the hill influenced the design, mirroring the curved walls and buried timber posts. Once the saplings and the green roof grow, the treehouse will be camouflaged.

Challenging access

Building on a muddy slope over winter, on a site only accessible by a very steep country lane, posed some challenges. The entrance was made wider for vehicles, requiring extensive ground works.

6 months to build

The client had a tight deadline, so rigorous planning and offsite manufacturing made the build as efficient as possible. A huge covered scaffold allowed them to work through winter in all weather.

Contact us

Get in touch

Our friendly team is always here to chat.

Email

Our friendly team is here to help.

info@livedin.co.uk

Office

Come say hello at our office HQ (by appointment only)

St Marys Mill, Chalford, Stroud, Glos

Phone

Mon-Fri from 9am to 5pm.

01453 733 913